"Xuzhou North Third Ring Road Viaduct" ground bridge main structure across the board
Date:2016/6/22 9:56:45 Browser:922

Our participation in "Xuzhou North Third Ring Road Elevated Expressway Bridge" project construction, in the construction of the Third Bureau held "work energetically for 100 days, after the realization of the four contact the main structure through the mobilization of the general assembly, on May 25, 2016 to achieve ground bridge main structure across the board through.


In the after 40 day and night rush to war, we completed the Beilei assembled more than 280 tons, scaffold erection 4 million multi, inside and outside the template installation of more than 10000 square meters, reinforcement of security more than 1200 tons, from May 8 to May 25, completed four league eight times box girder concrete pouring 74 cubic meters, completed ahead of schedule in the construction of the Third Bureau given to our task. My company has also been awarded the meeting "excellent team".